HATTIESBURG, MISS. – Crews are making progress, and work is on schedule to repair the I-110 bridge near Bayview Ave. following a fire under the bridge in September.
Damaged concrete has been removed and replaced with new concrete. Bridge columns are being repaired, and crews are finishing epoxy grouting on the columns this week.
Remaining work includes fiber wrapping the columns and additional cleaning.
The repairs are on track to be completed by the end of the year. Traffic should not be impacted as repairs are finalized. Motorists are reminded to be on high alert for roadside workers.
The $479,700 repair contract was awarded to Key, LLC, of Madison.