Schedule changes for Long Beach Railroad Crossing Improvement Project
LONG BEACH, Miss. (WXXV)- Schedule changes have been announced for the ongoing railroad crossing improvement project in Long Beach.
Due to utility lines interfering with planned work at the Nicholson Avenue intersection, Moran Hauling will shift efforts to several other railroad crossings while utility companies work to relocate their infrastructure.
Engineering firm Neel-Schaffer and Contractor Moran Hauling have coordinated with the paving subcontractor to move forward with crossings that require only asphalt resurfacing.
Work on these crossings will cause traffic alterations and periodic closures to ensure safety and efficiency.
The updated railroad crossing schedule is as follows:
- South Lang Avenue April 7 – April 9
- Trautman Avenue April 10 – April 11
- Girard Avenue April 14 – April 16
- Beach Park April 17 – April 18
- White Harbor April 21 – April 25
Motorists are encouraged to plan alternate routes during this period and follow posted signage for detours and safety guidance.